Storage service tariffs
In accordance with Article 21.2 of Annex A (RAST) of the Resolution 67/2019/R/gas and based on the revenues approved by Resolution 379/2023/R/gas, Edison Stoccaggio publishes here below storage service charges valid from 01/04/2024.
Space Cs = 0,208985 €cent/kWh/year*
Injection CI = 17.918018 €cent/kWh/day/year*
Withdrawal CE = 22.910922 €cent/kWh/day/year*
Note * : the tariffs are calculated on the basis of the revenues approved by Resolution 379/2023/R/gas and the offered capacities.
Charges for Irregular Deposit Service
Please note that it is ongoing, with the Responsible for Balancing and the other storage operators, an organic and coordinated revision of the Network Code and Storage Codes in the parts relating to the Real Guarantee on the gas in favour of third parties and the Deposit Service. The proposal to update the Code of Edison Stoccaggio will be published for consultation following the proposal to update the Network Code by the Responsible for Balancing.
In relation to the article 5.9.4 of the Code of Edison Stoccaggio (the version on the website is being updated), ARERA, with Resolution 355/2024/R/gas, approved following fees:the fees charged for the Irregular Deposit Service:
- no charge if the gas is in favour of the Responsible for Balancing;
- 1,000 EUR if the gas is in favour of other "third party" entities such as credit institutions or other users.
Please note that upon successful completion of the process of approval of the proposal, Edison Storage will apply the fees established in the version of the code approved by ARERA.
The documentation on the Real Guarantee to Third Parties and the Contract for the Irregular Deposit Service are published at the page Forms.